Work Schedule — Updated

Below I have divided the tasks in three-week interval which a line progress reports.

Final Delivery (7/22)

  • Finish data presentation website
  • Peer reviewed
    • Make edits/modifications
  • Complete report

Whole Semester (4/20 - 7/22)

Throughout the semester I will spend time gaining knowledge on the follow as it relates to my project:

  (Notes and Resources will be posted in the organizations github repos)

Accomplishments

Progress Report 1 (Due 5/9)

  • Start Project
    • Proposal
  • Do some data research
  • Find data sets to work with
  • Create github organization
  • Host the website in main repo

Progress Report 2 (Due 5/30)

  • Load in the data sets
    • Look through the data set
  • Data_Push R package (Data host repo)
  • Start wrangling
  • Make basic visualizations to see the data
  • Develop YML file

Progress Report 3 (Due 6/20)

  • Wrangle and Visualize data
    • Non-interactive plots
    • Interactive plots

Progress Report 4 (Due 7/11)

  • Last steps website
    • Finalize visualizations
    • Finalize YML
    • Finalize tibbles
  • Start report

Hour Break Down

kable(dt)
Description Time (decimal)
Proposal 8.33
Ethics 3.83
ePortfolio/Resume 13.08
Viz 32.83
Package 2.00
Datasets 29.08
Data Driven 9.50
GitHub 1.75
Jobs 19.67
Progress Report 9.17
Tidy Tuesday 5.50
Website 5.33
Total 140.08

Observations

I was able to finish tibbles and am almost done with the Visualizations. I am getting an error with my leaflets. The error says: Error in polygonData.default(data) : Don’t know how to get path data from object of class tbl_df. I am also almost completed with the yaml. I have also started with Yaml file for the website. I believe I am on track to finish if I can figure out my error, I posted the error on BYUI-datascience slack channel. I will fix my error when I find out what the solution is.